Project Title
|
Client
|
Project Value (mil)
|
YearCompleted
|
|
Contract 3203 Upgrading Of Telok Blangah Road To Semi-Expressway (From Kampong Bahru Road To Henderson Road)
|
Land Transport Authority Singapore
|
S$83.8
|
2001
|
|
*MRT North East Line Contract 702 Construction And Completion Of Sengkang And Buangkok Stations Including Tunnels
|
Land Transport Authority Singapore
|
S$166.381
|
2002
|
|
*MRT North East Line Contract 712 Construction And Completion Of Punggol Station Including Tunnels
|
Land Transport Authority Singapore
|
S$85.8695
|
2002
|
|
Contract RR0002 Bridge Across Jurong River
|
Land Transport Authority Singapore
|
S$25.581
|
2005
|
|
Contract 821 Construction And Completion Of Kim Chuan Depot
|
Land Transport Authority Singapore
|
S$296.550
|
2007
|
|
The Construction Of Aircraft Parking Apron, Associated Taxiways & Ancillary Works At Singapore Changi Airport Contract No. EN/ADT3/2001/11
|
Civil Aviation Authority Singapore
|
S$52.154
|
2007
|
|
Contract RR0201 PIE/Toh Guan Road Interchange and Toh Guan Road Extension to PIE
|
Land Transport Authority Singapore
|
S$20.792
|
2005
|
|
Contract ER158 Bridge over Sungei Serangoon Connecting Buangkok Drive To Tampines Road
|
Land Transport Authority Singapore
|
S$33.918
|
2009
|
|
Contract 3370B Completion Contract for Extension of Bartley Road to Airport Road
|
Land Transport Authority Singapore
|
S$51.600
|
In progress will be completed 2009
|
|
Supply of Building Materials
|
Housing & Development Board
|
S$78.58
|
2007-2008
|
|
Contract 901 Construction And Completion of Marina Bay Station Including Associated Tunnels for Downtown Line Stage 1
|
Land Transport Authority Singapore
|
S$348.4
|
In progress will be completed 2011
|
|
Contract 481 Design, Construction And Completion of Marina Coastal Expressway (Marina Wharf)
|
Land Transport Authority Singapore
|
S$305
|
In progress will be completed 2013
|
|
*Contract 911 Design and Construction of Depot for Downtown Line
|
Land Transport Authority Singapore
|
S$410
|
In progress will be completed 2015
|
|
Supply of Building Materials
|
Housing & Development Board
|
S$10.21
|
2009-2010
|
|
Supply of Building Materials for the HDB
|
Housing & Development Board
|
S$7.7
|
April 2010 - March 2011
|